Loveland Elementary

 

FACILITY IMPROVEMENTS/RECOMMENDATIONS

    Phase I: Implement high-priority improvements

    • Security - Entrance vestibule
    • Safety - Safe area for students
    • Building Envelope - Miscellaneous repairs
    Phase III: Construct new elementary on same site

 

BUILDING INFORMATION AND FACTS

    Year Constructed: 1932
    Additions/Renovations: 1951, 1954, 1973, 1985, 1997
    Gross Building Area: 34,524 SF
    Site Area: 2.5 Acres
    Number of Sections: 2
    Temporary Structures: 2,013 SF
    Phase I Project Value: $486,000
 
 

RECENT UPDATES

     Community Engagement
   
 
  • Conducted community club information session for scope of work on February 22, 2016.
  • ​Neighborhood expressed concerns with the area of refuge aesthetics.
  • Project Advocates met with representatives from the neighborhood to review the are of refuge elevation and received positive feedback.
     Construction
   
 
  • Ronco and PA are currently reviewing subcontractor pricing in preparation for the final GMP.
  • Soil borings have been completed for all associated work.
  • ​​CM is currently procuring sub-contractor and vendor.
  • ​Preplanning meetings for moves and site logistics are underway.
  • Construction work started 5/2/16 (relocating portable classroom).
  • Existing sanitary resolution complete.
  • Area of refuge footings complete.
  • Precast erection to commence.
  • Portable removed.
  • Existing electrical and water resolution complete.
  • Area of refuge interior framing and rough-ins complete. Drywall starting.
  • Main entrance new doors and frames in progress.
  • New lunch tables installation in progress.
  • Security rough-ins in progress.
     Design Development
   
 
  • DLR will present Design Development drawings to the Board of Education for approval on April 25, 2016. 
     Final Design
   
 
  • On March 10, 2016 the Zoning Board of Appeals approved the waiver to base the capacity of the area of refugee on actual enrollment.
     Pre-Construction
   
 
  • School and district staff preparing areas for renovation work to begin.
  • Permitting process complete.
  • Finalizing CMR GMP, ​complete by mid-May.
  • Submittal process underway.
  • Preconstruction meetings with CM and Principal complete.
 