Paddock Elementary

 

FACILITY IMPROVEMENTS/RECOMMENDATIONS

    Phase I: Implement high priority improvements

    • Security - Entrance vestibule
    • Safety - Safe area for students
    • Building envelope - Miscellaneous repairs
    Phase II: Renovation/Additions to be completed

    • Construct new gym
    • Introduce project-based learning spaces
    • Reconfigure and expand administration area
    • Improve special education spaces
    • Improve ADA access (interior and exterior)
    • Upgrade HVAC systems
    • Improve pick-up and drop-off
    • Add dedicated art and music/world language space
 

BUILDING INFORMATION AND FACTS

    Year Constructed: 1961
    Additions/Renovations: 1962, 1972, 2003
    Gross Building Area: 38,841 GSF
    Site Area: 9.1 Acres
    Number of Sections: 2
    Temporary Structures: 0 SF
    Phase I Project Value: $858,000
 
 

RECENT UPDATES

     Community Engagement
   
 
  • ​Conducted community club information session for scope of work on March 1, 2016.
     Construction
   
 
  • MCL and PA are currently reviewing subcontractor pricing in preparation for the final GMP.
  • ​Soil borings have been completed for all associated work.
  • ​CM is currently procuring sub-contractor and vendor.
  • ​Preplanning meetings for moves and site logistics are underway.
  • Construction work on track to start 5/25/16.
  • Boiler replacement in progress.
  • Area of refuge excavation and footings in progress.
  • Area of refuge finishes ready to start.
  • Soffit repairs nearly complete.
  • New fire alarm installation in progress.
  • ​Entry vestibule installation to start.
  • Security installation in progress.
  • Boiler replacement in progress.
     Demolition
   
 
  • Demolition exterior and interior complete.
     Design Procurement
   
 
  • ​Materials, submittals and procurement in progress.
     Preconstruction
   
 
  • School and district staff preparing areas for renovation work to begin.
  • Permitting process complete.
  • Finalizing CMR GMP, complete by mid-May.
  • Submittal process underway.
  • Preconstruction meetings with CM and Principal mid-May.
  • Asbestos removal in boiler room complete.
 