FACILITY IMPROVEMENTS/RECOMMENDATIONS

    Phase I: Implement high-priority improvements

    • Security - Entrance vestibule
    • Safety - Safe area for students
    • Building envelope - Miscellaneous repairs
    Phase II: Renovation/Additions to be completed

    • Construct new gym
    • Introduce project-based learning spaces
    • Reconfigure and expand administration area
    • Improve special education spaces
    • Upgrade HVAC systems
    • Improve pick-up and drop-off
    • Improvements to media center
    • Relocate early childhood classrooms to optimize logisitics
    • Introduce more natural light into learning areas
    • Add dedicated art and music/world language space
    • Separate gym and cafeteria
 

BUILDING INFORMATION AND FACTS

    Year Constructed: 1959​
    Additions/Renovations: 1962,1982
    Gross Building Area: 40,387 GSF
    Site Area: 6.5 Acres
    Number of Sections: 2
    Temporary Structures: 0 SF
    Phase I Project Value: $1,205,000
 
 

RECENT UPDATES

     Community Engagement
   
 
  • ​Conducted community club information session for scope of work on February 25, 2016.
     Construction
   
 
  • MCL and PA are currently reviewing subcontractor pricing in preparation for the final GMP.
  • McGill Asbestos Contracting has been awarded abatement services.  Work to commence at end of current school year.
  • Soil borings have been completed for all associated work.
  • ​CM is currently procuring sub-contractor and vendor.
  • Preplanning meetings for moves and site logistics are underway.
  • Construction work on track to start 5/25/16.
  • Area of refuge excavation and footings in progress.
  • Interior layout and framing to begin.
  • Interior framing and drywall nearly complete. Finishes ready to start.
  • Area of refuge in progress.
  • Security installation to start.
  • Life to stage starting.
     Demolition
   
 
  • Demolition (interior and exterior) in progress.
     Preconstruction
   
 
  • School and district staff preparing areas for renovation work to begin.
  • Permitting process complete.
  • Finalzing CMR GMP, complete by mid-May.
  • Submittal process underway.
  • Preconstruction meetings with CM and Principal mid-May.
  • Asbestos removal complete.
  • Material and submittal procurement in progress.
 