Sunset Hills Elementary

 

FACILITY IMPROVEMENTS/RECOMMENDATIONS

    Phase I: Construct new two-section school on same site.

    • Optimize site size and layout
    • Improve drop-off and pick up safety
    • Improve convenience for ADA access
    • Relocate office/administration area at the main entrance for security
    • Right-size classrooms
    • Introduce project-based learning areas
    • Improve security
    • Add special education spaces
    • Add separate gym and cafeteria
    • Add dedicated art and music/world language space
    • Provide storm shelters as required per building code​
 

BUILDING INFORMATION AND FACTS

    Year Constructed: 1956
    Additions/Renovations: 1982, 1997
    Gross Building Area: 26,862 GSF
    Site Area: 11.5 Acres
    Temporary Structures: 0 SF
    Phase I Project Value: $13,824,000
 
 

RECENT UPDATES

     Construction
   
 
  • Painting ongoing in all area's of the school​, Millwork being installed in all areas, Door installation ongoing, and Flooring scheduled to commence week of May 14th.
  • ​Exterior sitework ongoing, playground installation ongoing, and preparing for landscpaing.
     Administration
   
 
  • ​Students will be out of school on May 14 and 15th, 2018. Staff will be packing for the upcoming move. Students will return to school on May 16, 2018.
 