Exterior brick on building ongoing.
-
MEP interior rough in's ongoing in area A, B and C.
-
Interior metal stud framing completed in area B, and C.
-
Hanging Drywall in area C, B and A
-
Taping and Mudding Drywall in area C, B and A
-
Site work schedule to begin third week of March, 2019.
-
Exterior construction is progressing even through the inclement weather.
-
Gym equipment is installed.
-
Casework installation has started.
-
Mechanical Commissioning on target.
-
Paving site has potential slip.
-
Site work scheduled to begin early April.
|