Westside Swing School And Career Center

 

FACILITY IMPROVEMENTS/RECOMMENDATIONS

    Phase I: Renovation/Additions to be completed

    • Building envelope - Miscellaneous repairs
    • Electrical - Miscellaneous upgrades
    • Security - Install security vestibule, door access, and cameras
    • Convert upper level to two-section elementary swing school
    • Convert lower level for Career Center and CAPS program students
 

BUILDING INFORMATION AND FACTS

    This information is coming soon. Please check back later for updates.

 

RECENT UPDATES

     Construction
   
 
  • ​Vrana was awarded GMP #2
  • Carpet, Millwork, Tile, Painting, MEP Trim, and Ceiling being installed in Lower Level
  • West Campus will move over spring break to their new location in lower level.
  • ​Vrana Construction was awarded GMP#2
  • ​West Campus renovation completed on lower level.
  • ​West Campus move was completed to the Lower Level over spring break.
  • ​West Campus students have resumed school in the lower level as of April 4, 2016.
  • ​Selective demolition has begun on Upper Level swing school.
  • ​Asbestos abatement has begun on Upper Level swing school.
  • Selective Demolition and asbestos abatement continues on Upper Level swing school.
  • Construction of Pre-K entrance has begun.
  • Underground MEP complete.
  • Metal stud framing continues on POD's A and B.
  • MEP wall rough-in continues in POD's A and B.
  • Drywall has started in POD's A and B.
  • Grid ceilings scheduled to start in POD's A and B the week of May 8, 2016.
  • Construction of pre-k entrance continues.
  • Underground MEP complete.
  • Final painting and carpet installation continues in PODs A and B.
  • Demolition continues in PODs C and D.
  • Playground installation continues.
  • Drywall continues in PODs C and D​.
  • Playgound installation continues.
  • Finishes being completed in all PODs.
  • Final cleaning scheduled for July 15, 2016.
  • Playground installation continues.
     Planning
   
 
  • Move-in scheduled for July 18, 2016.
     Preconstruction
   
 
  • Asbestos abatement complete on upper level swing school.
 