Westbrook Elementary

 

FACILITY IMPROVEMENTS/RECOMMENDATIONS

    Phase I: Implement high-priority improvements

    • Security - Entrance vestibule
    • Safety - Safe area for students
    • Building envelope - Miscellaneous repairs
    Phase II: Renovation/Additions to be completed

    • Create pick-up and drop-off at main entrance
    • Add restrooms to kindergarten classrooms
    • Right-size classrooms (kindergarten)
    • Improve special education spaces
    • Introduce project-based learning spaces
    • Relocate office/administration area
    • Replace HVAC system
    • Add dedicated art and music/world language space
 

BUILDING INFORMATION AND FACTS

    Year Constructed: 1959
    Additions/Renovations: 2005
    Gross Building Area: 95,921 GSF
    Site Area: 13.5 Acres
    Number of Sections: 3
    Temporary Structures: 0 SF
    Phase I Project Value: $1,232,000
 
 

RECENT UPDATES

     Community Engagement
   
 
  • ​Conducted community club information session for scope of work on February 4, 2016.
     Construction
   
 
  • Ronco and PA are currently reviewing subcontractor pricing in preparation for the final GMP.
  • McGill Asbestos Contracting has been awarded abatement services.  Work to commence at end of the current school year.
  • ​CM is currently procuring sub-contractor and vendor.
  • ​Preplanning meetings for moves and site logistics are underway.
  • ​Mechanical enhancement is being funded via a special building fund.
  • Construction work on track to start 5/25/16.
  • New sewer tie-in in progress.
  • Interior layout and construction to commence.
  • Interior framing and drywall nearly complete. Finishes scheduled to start.
  • New boiler installation in progress.
  • Unit ventilation control valves in progress.
  • Area of refuge door enhancement nearly complete.
  • Stage lift in progress.
  • Security installation in progress.
     Demolition
   
 
  • Demolition in progress.
  • Boiler demolition in progess.
     Preconstruction
   
 
  • School and district staff preparing areas for renovation work to begin.
  • Permitting process complete.
  • Finalizing CMR GMP, complete by mid-May.
  • Preconstruction meetings with CM and Principal mid-May.
  • ​Asbestos removal complete.
 